What the master of general construction works does. Profession: master of general construction works. current provision of food, clothing, shoes, soft equipment, household items, personal hygiene, medicines, funds for cultural masses

STANDARD OF THE RUSSIAN FEDERATION

EDUCATION: PRIMARY PROFESSIONAL EDUCATION

─────────────────────────────────────────────────────────────────

OST 9 PO 02.22.3-2000

Official edition

─────

Agreed Approved

Division educational institutions Deputy Minister

Gosstroy of the Russian Federation

Letter N 28-9 / 341

STANDARD OF THE RUSSIAN FEDERATION

EDUCATION: PRIMARY PROFESSIONAL EDUCATION

────────────────────────────────────────────────────────

PROFESSION: MASTER OF GENERAL CONSTRUCTION WORKS

OST 9 PO 02.22.3-2000

Official edition

Agreed Approved

Department of Educational Institutions Deputy Minister

and advanced training of education of the Russian

Gosstroy of the Russian Federation

Letter N 28-9 / 341

STANDARD OF THE RUSSIAN FEDERATION

EDUCATION

────────────────────────────────────────────────────────────────────────

Initial vocational education

2Profession: general builder

work OST 9 PO 02.22.3-2000

2Profession: waid-range master in

building industry

────────────────────────────────────────────────────────────────────────

Date of introduction

Explanatory note

to the federal component of the State educational stan-

dart primary vocational education by profession "Master

general construction works "

Federal component of the State educational standard

primary vocational education in the profession "Master of public

construction works "includes documents:

a) professional characteristics;

b) the federal component of the content of the professional cycle

The organization of training by profession is carried out on the basis of the List

nya professions and specialties of primary vocational education

Documents defining the federal component of the content of general technical

nological and industry training cycles are standards

3.QUALIFICATION

In the system of continuing education, the profession "Master of General Construction

tel work "refers to the 3rd level of qualification.

Level general educationrequired for the profession

Average (complete) general; vocational education - primary

professional.

OST 9 PO 02.22.3-2000 S.5

Tariffication of works by profession "Master of general construction works"

established by the enterprise together with an educational institution in

in accordance with the tariffication system in force in the country (industry).

Advanced training of the "Master of General Construction Works" carried out

is set:

In institutions of primary vocational education and

enterprises with the aim of updating and expanding knowledge and skills, as well as

obtaining professional qualifications in new specialty in frame-

kah profession.

In the system of continuing professional education to achieve

a higher level of qualification in this area (industry)

professional activity on the basis of secondary specialized educational institutions

________________________________________________________________

Types of professional │Theoretical foundations of professional

activities onal activities

──────────────────────────────────┼──────────────────────────────

──────────────────────────────────┴──────────────────────────────

21. General professional parameters

Performs the simplest stone, technology of the simplest stone

furnace, assembly, electric welding, stove, furnace, assembly, electrical

sling, concrete, reinforcing welding, sling, concrete

work and reinforcement works

Performs masonry and repair ka - The main types of wall materials

changeable structures of buildings, bridges, rials

industrial and hydrotechnical methods of preparation of ras-

structures of thieves

Punches nests, furrows and methods of punching nests, furrows

holes in brick and rubble and holes in brickwork

masonry, concrete and reinforced concrete

structures

Disassemble by hand rubble pounds - Rules for disassembling masonry

damnts, brickwork of walls of dams, walls and pillars, pe-

pillars, uncoated ovens and ku - whose

hone hearths, formwork of the simplest Basic types of rigging

tooling designs

Places brick posts under the Bricklaying Rules

genital lags of columns

С.6 OST 9 PO 02.22.3-2000

Fills channels or ducts according to - Tools and accessories

roshkogo materials or finesse used for stone

masonry and installation

neral wool for building structures

Sets Metal Temporary Installation Technology

temporary suspension furnaces with metal furnaces

Cleans and scrapes the facial

the surface of the ovens for operation and maintenance

equipment, devices and

instruments

Performs the simplest work with the main types of slings, gripping

assembly of steel and prefabricated concrete fixtures, rigging

ny and reinforced concrete structures equipment

Performs the simplest welding device of machines and mechanisms

work, uses manual and electric - for the production of welding

triified tools and works

construction machines and fur - The principle of operation of electric

nizmami of hard machines and devices

Performs surfacing of simple neot - Rules of maintenance of electrical

critical parts of welding machines

Performs slinging and lashing of loads - Rules for slinging standard

call of various lengths and weights of products

Rules for slinging, lifting and

moving various loads

Design features

lifting devices

(slings, traverses, grabs and

Specifications

hoisting cranes and

safety requirements when working

self-propelled boom boom

new near power lines

OST 9 PO 02.22.3-2000 S.7

┌─────────────────────────────────┬───────────────────────────────┐

└─────────────────────────────────┴───────────────────────────────┘

Basic provisions about the system

occupational safety standards

Monitors the load when lifting, Permissible load of the slings

moving and laying and ropes

Performs the simplest work with the methods of cooking ras-

preparation of concrete mix and uk - thieves and concrete mixes by hand

its structure in new

Methods for notching concrete

surfaces

Carries out notching of concrete surfaces - Methods for feeding concrete mixes

surfaces in the design

Accepts concrete mix and Concrete care rules

prepares solutions manually

Dispenses components during disassembly - Techniques and rules for disassembly

power of devices by weight and volume - concrete and reinforced concrete

him (wheelbarrows, measurers) of structures, laying of foundation

tov, walls and pillars

Formwork disassembly methods

simplest designs

Disassembles concrete and reinforced concrete - The main types of wall

toned designs by hand of materials and materials, including

trumped during production

stone oven works

Methods for installing metal

personal temporary ovens

Engages steel concrete and requirements

reinforced concrete structures Inven - to the quality of the work performed,

with tare slings for mounting loops - including for adjacent operations

whether, staples, hooks, etc. to radios or processes

Sorts, unwinds, cuts, Rules and methods of unwinding

straightens, bends, pulls ar - and cutting of reinforcing steel

matte wire by hand swans - Rules of transportation and

kami, on manual storage machines for finished frames-

С.8 OST 9 PO 02.22.3-2000

┌──────────────────────────────────┬───────────────────────────────┐

└──────────────────────────────────┴───────────────────────────────┘

Prevents and eliminates de - Types of defects and their methods

elimination works

Complies with safety rules Labor safety rules

22.Special parameters

2A. Profession - bricklayer

Lays simple brick walls The main properties of wall materials

and small blocks for plastering and materials and mortars, as well as

with jointing along the masonry; waterproofing materials,

lays foundations of bricks and used for insulation functions

reinforced concrete products; lays dams and walls

walls and corners of buildings

Fills in framed walls Simple systems masonry and re-

knitting seams

Arranges foundations from rubble - Techniques for laying simple walls

th stone and brick rubble under

bay; performs laying of the foundation,

corners of the building

Arranges a cement screed, Methods for spreading mortar

on the wall, brick layouts and

Arranges horizontal hydro - Pneumatic operating rules

insulation of the foundation with roll and electrified tools

materials cop

Seals with brick and concrete Main types of parts and assembly-

furrows, nests and openings used

when erecting stone buildings

and facilities

Penetrates openings in brick and brick quality requirements

concrete walls. masonry and precast concrete

structures mounted in the

change buildings

Performs installation in stone buildings - Reinforced concrete installation technology -

reinforced concrete lintels

over window and doorways

OST 9 PO 02.22.3-2000 S.9

┌──────────────────────────────────┬───────────────────────────────┐

└──────────────────────────────────┴───────────────────────────────┘

2B. Profession - stove-maker

Arranges foundations and lays down Basic requirements applied to

the foundations for the furnaces are washed to the quality of bricks and concrete

Lays stoves of temporary type with Methods of laying foundations for

Establishes and strengthens stove methods for laying temporary stoves

Sorts and matches by color Simple suture dressing systems

(shade) stove tiles

Rubs the edges of tiles Methods of disassembling lined

stoves, hogs and chimneys

Prepares solutions from Vertical construction methods

gzhel and refractory clay cutting

2B. Profession - steel erector

2 and reinforced concrete structures

Performs cleaning of assembled main types of steel parts

structures and prefabricated concrete and reinforced

ton structures

Performs fastening of assembly types of the main rigging and

bolts of connections of installation equipment and

aptitudes

Makes the installation of self-tapping - Rules for transportation and

storage bolts of structures and

P.10. OST 9 PO 02.22.3-2000

┌──────────────────────────────────┬───────────────────────────────┐

└──────────────────────────────────┴───────────────────────────────┘

Checks with kerosene and chalk Devices and methods of

welds when checking their interchangeable fastening of structures

density

Ruled by shaped steels on hand Simple ways weld checks

screw press seams

Lays paving slabs - Basic properties and grades are

tiy ton mixtures

Provides temporary fastening Rules for surface preparation

structures for insulation

1.1.3. General construction works: purpose, types, volumes.

Stone works: types, classification depending on the type

masonry and materials used.

Furnace works: types, purpose, technology of laying furnaces,

applied material.

Installation work: purpose, types, classification depending on

bridges from the structures used.

Electric welding: purpose, classification of welding

depending on the materials used.

Slinging works: purpose, types, classification of slings

depending on cargo of different mass

Concrete work: purpose, types, classification depending on

bridges from structures and materials used.

Reinforcement work: purpose, classification depending on

ruments.

P.18 OST 9 PO 02.22.3-2000

1.1.4. Tools, mechanisms, devices, for general construction

technical work: purpose, classification, device, technical

specifications.

Control and measuring devices: purpose, device,

operating rules.

Hand power tools.

Selection and use of tools and devices.

1.1.5. Solutions: types, methods of preparation of solutions

personnel.

Determination of the composition of solutions and the size of the fill

Checking the fluidity of the solution (2)

Neutralizing compounds: types, methods of preparation.

1.1.6. Preparation of reinforcing steel for work: the main types,

the sequence of operations for knitting frames.

1.1.7. Preparation of concrete mix for laying in a structure:

main types, sequence of operations.

1.1.8. Preparation of foundations for the bay and furnaces: types, methods

would be masonry, requirements for masonry, the sequence of performing the operation

1.1.9. Preparation of goods for slinging: types, weight, height, size

measurements, conditional signaling.

Requirements for the safe conduct of work for slingers.

1.1.10. Preparation of parts for welding: types of applied material

1.1.11. Materials for general construction works: classification,

purpose, application, composition, properties.

Manual basic mixes (2)

Surface application (2)

OST 9 PO 02.22.3-2000 S.19

22. SPECIAL STONE UNIT

22.1. Stone technology

2.1.1. Wall materials and solutions: types, purpose, properties

tva, compositions, recipes and methods of preparation of solutions.

2.1.2. Tools: types, purpose, classification, application

nie, rules of work and care.

Selection and use of tools and devices (2)

2.1.3. Methods of laying and bandaging seams (2). Requirements for quality

masonry (2)

2.1.4. Laying of stone structures, buildings, bridges and co-

guns: sequence of operations (2).

Installation of foundations, cement screed, waterproofing: pos-

research and features of the work.

Technology for performing preparatory and auxiliary

masonry operations (2)

2.1.5. Technology of mounting reinforced concrete lintels over windows

ny and doorways and niches (2)

23 0.2 SPECIAL OVEN UNIT

23.1 Furnace technology

3.1.1. Basic materials and solutions: types, purpose, composition

tav, properties, methods of preparation of special solutions.

Preparation of solutions from Gzhel and refractory clay (2).

Filling cracks in the oven masonry with clay mortar (2)

3.1.2. Suture dressing systems (2).

P.20 OST 9 PO 02.22.3-2000

3.1.3. Stove appliances and tiles: types, purpose, classification

tion, technology of installation and replacement of furnace devices (2)

Selection by color, sorting and grinding of stove tiles (2)

Performing work on replacing devices in unlined furnaces (2).

3.1.4. Laying furnaces, hearths and pipes: methods of laying foundations

goods under the oven, technology of the base device, sequence

brickwork and disassembly of ovens (2).

Dismantling the lined furnace (2).

24. SPECIAL UNIT OF INSTALLER FOR INSTALLATION OF STEEL AND

2 REINFORCED CONCRETE STRUCTURES

4.1.1. The main rigging, installation equipment and accessories

possessions: types, purpose, rules of transportation and storage

Slings and grippers: types, purpose, right-

for application (2).

Fastening structures: sequence of operations

tions, signaling rules during installation (2).

Sealing furrows, nests, potholes and holes (2)

4.1.2. Loading and unloading and storage operations (2).

4.1.3. Installation of prefabricated partitions and internal walls:

sequence of operations (2).

Performing the simplest work on the installation of steel and reinforced

ton structures (2) .Checking of welds (2).

cutting bolts (2).

OST 9 PO 02.22.3-2000 S.21

25 SPECIAL UNIT OF ELECTRIC WELDER

25.1.1. Electro technology welding works

5.1.1. Preliminary preparation of welding consumables:

dy, purpose, sequence of operations.

5.1.2. Electric welding machines and devices: types, purpose,

classification, device, specifications, regulations

maintenance and operation (2)

5.1.3. Control and measuring devices: types, purpose,

application, causes and remedies for defects

electric welding works (2).

5.1.4. Preparation of products and units for welding: sequential

work performance (2)

Surfacing of simple irrelevant parts (2) Protection of the welded

seam during welding (2).

26. SPECIAL BLOCKER UNIT

26.1. Slinging technology

6.1.1. Cargo: variety, classification depending on

weight, volume, length, various dimensions, flowability.

6.1.2. Lifting devices: types, purpose, application

Slinging and lashing of goods: types, purpose. methods and pos-

sequence of operations (2)

Movement and strapping methods (2).

Rules and requirements of Gosgortekhnadzor of Russia for safe

operation of lifting equipment (2).

P.22 OST 9 PO 02.22.3-2000

27. SPECIAL CONCRETE UNIT

27.1 Concrete technology

7.1.1. Preparation of concrete mix: general concepts, types be-

tonomixers, device, performance, storage methods and

transportation.

7.1.2. Cement: types, purpose, classification of binders

and additives (2).

Water: composition, properties, purpose, requirements, presenting

dispensed to water.

7.1.3. Concrete transportation: purpose and characteristics

theristics of machines for transporting the mixture, requirements, permissible

short terms of transportation of ready mixes, preventive measures

delamination and drying of the concrete mixture.

7.1.4. Concrete laying: rules and methods.

Concrete mixing machines: principles

organization of work on machines, characteristics of belt conveyors

ditch, concrete pavers, concrete mixing equipment

ki and in the shop.

7.1.5. Standards of time and production for laying and compaction of

ton of mixture.

7.1.6. Methods of concreting structures: techniques for laying

ton mix in foundations, bases and massifs (2)

Formwork: types, purpose, designs, sequence of installation

new and dismantled formwork of various designs (2)

Dismantling the formwork of a simple structure (2)

P.23 OST 9 PO 02.22.3-2000

28.Special reinforcement unit

28.1 Reinforcement technology

8.1.1. Basic information about reinforcing steel: types, purpose

nie, assortment (2).

Methods for cleaning, straightening, pulling, straightening reinforcement

steel (2)

Unwinding, cutting and bending methods (2)

Preparation of reinforcing steel for reinforcement work (2).

8.1.2. Tools, fixtures, machines: a variety

purpose, device, principle of operation, handling rules,

production rates.

Selection and use of tools and devices (2).

8.1.3. Methods for marking the arrangement of rods and frames.

Techniques: knitting of rod nodes; assembly, installation and fastening

simple reinforcement and reinforcement structures; assembly and knitting of meshes and flat

frameworks on several templates (2).

Assembly and knitting of meshes and flat frames (2)

OST 9 PO 02.22.3-2000 S.24

Distribution of training time by profession

"Master of General Construction Works"

under the section "Professional training"

┌─────────────────────────────────────────────────────┐

│ Number of hours on the base │

├─────────────────────────┬┐──────────────────────────│

│basic general education basic general │secondary│

│nia without receiving secondary education from to-│ (complete - │

│ (full) general education-│ radiation of the secondary go) general-│

│ niya │ (full) general │go image-│

│ │ education │ calling │

│────────────────────────────────────────────│────────│

│ Terms of study │ │

├─────────────────────────┬──────────────────│────────┤

│ 1-2 years │ 3 years │ 1 year │

├─────────────────────────┴──────────────────┘─────── │

│ Professional training │

├──────────────────────────────────────────────────── │

│ Time reserve │

│ Consulting │

│ Exams │

└─────────────────────────────────────────────────────┘

THE DRAFT STANDARD DEVELOPED BY THE INSTITUTE FOR THE DEVELOPMENT OF PROFESSIONAL

OF EDUCATION OF THE MINISTRY OF EDUCATION OF THE RUSSIAN FEDERATION

Institute Director

development of professional

education of the RF Ministry of Defense

Deputy Institute Director

development of professional

education of the RF Ministry of Defense

Development Manager:

providing construction professions

telii IRPO, kp n.

Executor:

Head laboratory for methodological

providing construction professions

telii IRPO, kp n.

AGREED

Department of educational institutions and

professional development

Qualification - bricklayer (4th grade);

electric welder manual welding (3rd rank)

The standard term for the development of the program on the basis of basic general education with obtaining secondary (complete) general education - 2 years 5 months.

Objects professional activity :

Buildings and structures, their elements;

Materials for general construction works;

General construction technology;

Construction machines, small-scale mechanization tools, tools and devices for general construction work.

The civil works master will know:

Technology of stone, assembly and electric welding works;

The main types of wall materials, properties of wall materials and mortars, as well as waterproofing materials used to isolate foundations and walls;

Tools and accessories used for masonry and installation of building structures, basic equipment;

Requirements for the quality of work performed, including for related operations or processes;

Basic information about the device of electric welding machines and devices;

The principle of operation of electric welding machines and devices for arc welding of alternating and direct current;

Types of basic rigging and installation equipment and accessories.

The master of general construction works will be able to:

Carry out installation in stone buildings and reinforced concrete lintels over window and door openings and niches;

Carry out stone, installation and electric welding works;

Carry out masonry and repair of stone structures of buildings, bridges, industrial and hydraulic structures;

Laying simple walls made of bricks and small blocks under plaster and with jointing along the masonry, foundations made of bricks and reinforced concrete products, laying walls and corners of buildings, filling frame walls;

Carry out installation in stone buildings and reinforced concrete lintels over window and door openings and niches;

Carry out manual, electric arc and gas-electric welding of simple parts, assemblies and structures made of carbon steel in the lower and vertical positions.

Studied disciplines:

Fundamentals of Materials Science;

Fundamentals of Electrical Engineering;

Fundamentals of construction drawing;

Basics of technology for general construction works;

Life safety;

Occupational Safety and Health;

Entrepreneurial activity;

Implementation of stone works;

Welding works by manual electric arc welding.

Job opportunities: the graduate will be able to work in construction enterprises, as well as in other industries. The profession "Master of general construction works" is currently in demand in our region.

ELECTRONIC WORKBOOK PROFESSION "MASTER OF CIVIL WORKS" IN INDUSTRIAL TRAINING FOR THE I COURSE REMINDER Dear friends! An electronic workbook will help you replenish and consolidate your knowledge of the basics of the theory of stone technology. It contains questions and assignments on 17 vocational training topics that characterize the features of stone work. The proposed tasks are designed for your independence in learning activities and provides for work with a textbook and additional literature. You are given the opportunity to express your own opinion on the studied problem. In search of answers to these questions and tasks, you will be able to better understand the main thing, control yourself, find out what you know and can do, and what else needs to be repeated. I wish you interesting work! Legend - Question for reflection, recollection and consolidation t - Test, consolidation of theoretical knowledge † - Working with a book, reference literature Y - Exercise - Research and creative tasks - Solve problem K - Guess the crossword H / E - Erudition task CONTENTS 1. Topic: “Introduction to the profession. Labor safety rules, fire safety and electrical safety in training workshops "2. Topic:" Excursion to the construction site and industrial enterprises for the manufacture of building structures "3. Topic:" Excursion to a construction site and industrial enterprises for the manufacture of building structures "4. Topic:" Introduction to the organization of a bricklayer's workplace "5. Topic:" Tools, fixtures and fittings "6. Topic:" Installation ordering, tightening of moorings "7. Topic:" Preparation of masonry mortars of a given grade "8. Topic:" Preparation of masonry mortars of a given grade "9. Topic:" Types of masonry, cutting rules "10. Topic:" Working out techniques for laying bricks in a press "11 Topic: "Working out techniques for laying bricks in a joint" 12. Topic: "Working out techniques for laying a brick in a joint with mortar trimming" 13. Topic: "Working out techniques for laying a brick in a half-line" 14. Topic: "Orderly method" 15. Topic: "Step method "16. Topic:" Mixed method "17. Topic:" Verification work on the results of the first half of the year "1.1. Introduction to the profession 1.2. Labor safety rules, fire safety and electrical safety in training workshops 1. Topic: “Introduction to the profession. Occupational safety rules, fire safety and electrical safety in training workshops "2. Topic:" Excursion to a construction site and industrial enterprises for the production of building structures "Click on a brick 3. Topic:" Tour to a construction site and industrial enterprises for the production of building structures "Click on a brick Click on the brick Organization of the workplace 4. Topic: "Familiarization with the organization of the mason's workplace" 5. Topic: "Tools, fixtures and inventory" Click on the brick Production tool Control and measuring tool Scaffolding and scaffolding 6. Topic: "Setting order, tension mooring "Click on a brick 7. Topic:" Preparation of masonry mortars of a given grade "Click on a brick 8. Topic:" Preparation of masonry mortars of a given grade "Click on a brick 9. Topic:" Types of masonry, cutting rules "Click on a brick Rules for cutting a stone masonry 10. Topic: "Working out the techniques of laying bricks in a press" Click on the brick Instructional - technological map Press-on bricklaying 11. Subject: "Working out techniques for laying bricks in a flush" Click on a brick Instructional technological map Flush-in-flush laying 12. Subject: "Practicing techniques for laying bricks in a flush with mortar trimming" solution 13. Topic: "Working out techniques for laying bricks in a half-line" Click on a brick Instructional technological map 14. Topic: "An orderly way" Click on a brick Instructional technological map 15. Topic: "Stepwise method" Click on the brick Instructional technological map 16. Topic: "Mixed method" Click on the brick Instructional technological map 17. Topic: “ Verification work according to the results of the first half of the year "Click on the brick

 